9.6.1.6   Run Data Sync Job

You can run a data sync (synchronization) job.

 

Note: The Run Data Sync job can also be run via TrialMaster via the Export History page (Run > Export).

 

To run a data sync job:

1.       Access the Trial Configuration page. (See Configure a Trial for guidance.)

2.      Click the DataModel/Reporting tab.

3.       Click the Run Data Sync button. A confirmation message displays at the top that the data sync job was completed.